LORAN
 
 
  Originally Published: 12/02/2016
 
 
 
 
 
 
  (LORSTA Attu, May, 1945.)
  SECTION III
  CHAPTER 2
  The establishment of a three-station chain, plus a monitor station in the Bering 
  Sea, is a good example of the other side of the picture. The seven-unit system on 
  the Atlantic demonstrated the confusion resulting from "too many cooks in the 
  kitchen." While a certain amount of confusion is bound to result when attempting 
  the establishment of any station or outpost in the Bering Sea area, due to the 
  extreme climatic conditions, the speed and dispatch with which the first four 
  Alaskan units were put into operation is a tribute to the coordinated efforts of the 
  Coast Guard, the Navy and the Army.
  It is perfectly obvious from the start why all three services would necessarily 
  participate in such a project. The U.S. Coast Guard was by this time possessed 
  of full responsibility for the operation and maintenance of all Loran units under 
  the jurisdiction of the United States. The Navy, however, was the prime user of 
  Loran at sea, and the service most interested in obtaining speedy service from it. 
  The Army had not only been in possession of the various points in the Alaskan 
  and Bering Sea Area which they had wrested from the Japanese, but had to 
  remain in some force in that area to maintain these outposts. Therefore the Army 
  would often be the neighbors of the U.S. Coast Guard units. Interference with 
  their communications systems already established had to be avoided at all costs. 
  In addition, the army already had near several sites, much of the heavy 
  construction equipment necessary in the construction of the units and by 
  borrowing this from the Army, the Navy and Coast Guard could avoid 
  transporting such equipment into the area, where transportation is a major 
  problem.
  Practically all air transportation during construction was by courtesy of the Army. 
  In fact, the liaison between the various services was so excellent that within five 
  months from the issuance of the Navy directive, some of the units were on the 
  air. An excellent example of interservice cooperation will be found in excerpts 
  quoted from Lt. J. F. Martin's reports, later in this chapter.
  As soon as the Navy directive calling for the establishment of the first three 
  Loran units in the Bering Sea area was received by the United States Coast 
  Guard activity began to assemble construction equipment, supplies, etc., in 
  Seattle for early shipment of the sites.
  These first sites were located on St. Paul Island, St. Matthew Island, Umnak 
  Island, and a monitor to be established at Cape Sarichef. The code names given 
  these units in the order listed above were: peter, mike, uncle, yoke.
  Since the locations for a number of the proposed Aleutian Station were in the 
  forward and remote areas, and also because of the unsatisfactory progress made 
  by the employment of civilian contractors for general construction work it was 
  necessary and obviously most practicable to organize a special construction 
  detachment to perform this work. A group was formed of selected enlisted men 
  and officer personnel who were qualified by their pursuits for the many types of 
  construction work required.
  Five civil engineer officers were assigned by the Chief, Civil Engineering Division 
  for duty with CG Unit 26 (Condet Able) which was to undertake the construction 
  of the Aleutian and Bering Sea Chain of stations.
  Lt. James Cournow, USCG, was placed in charge of procurement of all material 
  and equipment at Headquarters, under Capt. Gill and Admiral Johnson and Lt. J. 
  F. Martin, USCG, was designated as Commanding Officer, Coast Guard 
  construction Detachment and made his early operating base Seattle and later 
  Dutch Harbor.
  Shipment of material equipment was begun in February 1943 to the West Coast. 
  Commanding Officers for construction and operations were selected and 
  departed for Seattle also in February.
  Throughout the month of March and early April all cargo designated for the 
  projected units was assembled, checked and prepared for further shipment. 
  Much of the construction equipment and tools was obtained from the Seabee 
  advance base stock already in California. The Army contributed some special 
  foods and clothing that its logistic experts had already developed for life on the 
  northern islands.
  On 12 April loading was begun and the liberty ship which carried the first cargo 
  of equipment, the USS JONATHAN HARRINGTON, with about 100 Coast Guard 
  construction and technical personnel on board, sailed shortly thereafter.
  According to the account given by Lt. J. G. Permar, Civil Engineering Div., USCG, 
  who sailed with her in charge of construction for Mike, they had an eventful trip. 
  En route to Kodiak, the vessel had a submarine alert, which after all hands 
  standing battle stations turned out to be a whale. The ship stopped at Kodiak to 
  unload some cargo and the Coast Guard personnel had two days liberty ashore 
  there. Then on Easter Sunday, 25 April the reached Dutch Harbor, where 
  unloading began at once. The unloading was concluded within two days.
  The CGC CLOVER had been assigned to assist in transporting the cargo on the 
  sites and the cargo was transshipped onto her with all speed. Then bad weather 
  set in and the CLOVER did not sail until early May.
  Expediency has its virtues as shown in the following excerpt from Lt. Martin’s 
  report of 19 May 1943:
  "On 16 May the cutter CLOVER sailed for site P-3 (Mike.) At this time she was 
  towing the small tank landing barge (borrowed.) When about 12 miles at sea the 
  barge was capsized owing the excessive towing speed, which was ten knots. 
  Efforts were made to right the barge at sea, but owing to conditions (climatic), 
  this could not be done, and upon orders of the writer it was towed back into the 
  harbor and beached. With the use of a large tractor it was righted and work was 
  commenced immediately to tear down and clean the engines. This work is 
  progressing favorably and it is estimated the barge will again be ready for use 
  about 24 May.
  "With the idea of getting work started, the CLOVER was ordered to sail for site P-
  1 (Peter) which she did at 0900 17 May. She arrived there at 1023 18 May and 
  work of unloading was started immediately. A dispatch has just been received 
  stating that his work was completed, and she is returning for the second and 
  final load of supplies. With the assistance of the Army detachment on the island 
  a road has been started from the landing along the bluff on south side of island 
  to site. There are about 300 men (Army) with considerable mechanical equipment 
  in this detachment and full cooperation is being given. Coast Guard construction 
  personnel to the number of thirty were taken on the first trip and these men are 
  remaining on the job under the direction Ensigns Permar and O'Meara."
  Thus it happened that Ensigns Permar and O'Meara who were originally destined 
  to handle construction on St. Matthew, ended up by building the unit on St. Paul 
  instead with a saving of time and effort on the part of all concerned.
  The cooperation of the Army detachment mentioned above is also representative 
  of all the detachments stationed anywhere near Loran sites in the entire area.
  Ens. Permar stated that another reason for diverting the original construction 
  unit from Mike to Peter was that following the capsizing of the barge; a wire was 
  sent the Army at St. Paul requesting the use of a lighter. The Army replied that 
  they could supply one for unloading there and with the aid of the Army the 
  CLOVER was unloaded within twenty-four hours after arrival at Peter. The 
  unloading point on this island was near a native village, which had just returned 
  to their homes in the village a few days before the arrival of the CLOVER. They 
  seemed very glad to see the Coast Guard arrive greeting them as old friends and 
  expressing pleasure that a station would be on their island.
  The materials at Peter were trucked for five miles over a road, then moved the 
  last three miles to the site in borrowed Army tractors and track type trailers. The 
  construction camp was set up at the three-mile point where the Coast Guard 
  personnel lived in tents, using an abandoned fox trapper's shack as galley.
  All land for the first three sites had to be obtained from the Secretary of the 
  Interior, by the Secretary of the Navy, as the sites were situated on either grazing 
  rights or wildlife sanctuaries. Silver and blue fox, reindeer, and Kodiak bear 
  populated the island and one unit required telephone repairs rather often as the 
  reindeer persisted in knocking down the wires with their antlers. The use of the 
  sites by the Coast Guard was granted for the duration and six months thereafter.
  The construction and installation of this particular unit proceeded with no undue 
  hardship on the part of the Coast Guard crew. The main difficulty was 
  encountered by the CLOVER, which found it difficult at time to maintain regular 
  unloading schedules at all the sites as the weather was always so uncertain in 
  that region that of ten she had to stand off for fog, and Peter, Uncle, and Yoke 
  had their share also. Within ten minutes so variable was the weather; the same 
  spot would experience bright sunshine, rain, then snow, and then fog.
  It seems unnecessary to cover in detail the construction of each separate site in 
  this chain as construction proceeded almost simultaneously at all four points, 
  and difficulties encountered at one would probably be duplicated at some time at 
  all of them.
  It was necessary at all four of the sites to remove the layer of muskeg before 
  building, as the muskeg was so spongy that no permanent erection could be 
  anchored to it. This was done with heavy Army "cats" and tractors. Special 
  precautions had to be taken in the erection of the antennae, as the winds there 
  are forceful and special guying was advisable. Often in the water supply proved a 
  problem, which in some cases was overcome by chlorination of the local supply 
  or in others by the use of evaporating units.
  Unlike the situation of the men constructing the original Atlantic Loran system, 
  the Coast Guard personnel in the North Pacific area suffered no shortage of food, 
  medical supplies, necessary construction supplies, etc., due to the excellent 
  combined logistics of the various Services participating in the program. Their 
  buildings were weather tight, their clothing was correct and adequate; they did 
  not have to await the pleasure of civilian contractors for the installation of their 
  plumbing, and health and morale were reported as uniformly good. On 4 July 
  1943 the Coast Guard crew stationed at Peter played the Army construction outfit 
  at softball. Army won.
  It is a tribute to excellent personnel work on the part of both the Army and Coast 
  Guard officers stationed on these islands that the personnel maintained such 
  harmonious relations, especially since the Coast Guard mess equipment and 
  sometimes pay exceeded that of the Army.
  While the Army, as has been shown, gave all possible construction aid, more 
  difficulty was encountered on some of the other islands in landing supplies and 
  equipment than at St. Paul. In some cases, the harborage was nil, in other 
  williwaw conditions prevailed and in others the site was extremely difficult to 
  reach from the landing point. However, all things considered there was a 
  minimum of friction delay and discomfort.
  Credit should be given the Commanding Officers and Construction Officers of 
  the U. S. Coast Guard who drew this first all-service assignment for their tact, 
  resourcefulness, and efficiency.
  The original officers for the first three units established and the monitor were as 
  follows:
  St Paul - "Peter"
  Construction - Ens. Permar 
  Commanding Officer - Ens Albert J. Preston
  St. Matthew - "Mike"
  Construction - Lt. (jg) Horder
  Commanding Officer - Ens. Barwick
  Umnak - "Uncle"
  Construction - Ens, J. J. O'Meara
  Commanding Officer - Ens. Drouin
  Cape Sarichef - "Yoke"
  Construction & Commanding Officer - Guy Bellinger, CRM
  During the construction period, all personnel were under the jurisdiction of the 
  Officer in Charge of Construction Detachment, USCG, Lt. Martin at Dutch Harbor, 
  Alaska. When test operations began the operating officers and crews came under 
  the jurisdiction of Lt. Comdr. Amos, USCG.
  It should be noted here, though without undue emphasis that the original 
  Commanding Officer of Uncle was considered unqualified, before construction 
  began, by Lt. Martin and Headquarters was so informed. He was shortly replaced 
  for this duty by Ens. Drauin who carried out the major part of the installation of 
  technical equipment and put the unit on the air. Mention is made of this situation 
  only for the reason that it emphasizes the necessity for careful selection 
  Personnel for all such specialized assignments as much time and effort can be 
  lost when such care is neglected at the start.
  Ens. O'Meara did not remain long at Peter, but proceeded to Umnak as soon as 
  weather permitted and carried out construction operations there. By July 15 1943 
  Peter was ready to go on the air test and Ens. Permar departed on that date on 
  the CLOVER to Dutch Harbor. Here he picked up a load for Uncle and upon 
  reaching there remained supervising construction for about a month until the 
  unit was ready to go on the air.
  With the order to construct these units, the decision was also reached by the 
  Navy to relieve NDRC of the onus of equipment production. This was effected 
  early in 1943 and technical equipment thereafter for all Loran units was obtained 
  through BUSHIPS. With this move, the last connection between NDRC and the 
  establishment of Loran units was beginning to be severed as Mr. Fletcher Watson 
  formerly Secretary for NDRC and an accomplished astronomer, accepted a 
  commission in the U.S. Navy and as Lt. Watson of Hydrographic covered the 
  charting job.
  It is of interest to note so poorly had the Bering Sea Islands been shown on all 
  available charts, that when the Loran Units went on the air testing there true fixes 
  proved the location of the various islands on existing charts to be as much as 
  several miles in some cases, out of position. For that reason Hydrographic 
  Office, USN has found it necessary to Loran re-chart practically the entire area.
  In July, 1943 a site survey party covered the Aleutian Islands and selected sites 
  for three more units of Loran at Amchitka, Attu and Adak, as Dutch Harbor was 
  considered too far away for efficient correlation of activity.
  It is not good historic practice to record the good and omit the bad when giving a 
  true record and therefore it must be admitted that although conditions and 
  delays were much worse in the Atlantic chain, the Pacific chains were costly in 
  loss of life. Although Mike had been listed as expendable it was not believed that 
  any of the losses of personnel in the Pacific area were due to enemy action 
  though there is some doubt in one case.
  During the testing period of the units, five enlisted men were lost. Mystery still 
  enshrouds the loss of these men who set out from Mike in a small boat for a 
  shoreline trip to an Army weather stations some nine miles away. Ensign E.T. 
  Barwick, USCG, C.O. at Mike reports as follows:
  "At 1500, 20 September 1943 boat crew consisting of HAGLUND, Floyd O. (220-
  806) RM1c, BREIMO, Elmer O. (538-953) Cox. (r), HAGEN, Edward C. (584-147) 
  RM3, SCHMOLL, Kenneth H. (506-786) RM3 (r), and MACLAND, Thomas L. (636-
  878) Sea. 1c (r), departed from this station.....the boat crew's orders were to pick 
  up a small gasoline engine generator formerly used by Army weatherman in 
  transmitting weather reports to St. Paul Army Garrison."
  The men, boat, and all equipment in the boat disappeared without a trace. 
  Searching parties were sent out along the shore to the destination of the boat's 
  crew and search was also made along the beach and by boat. At 1338, 24 
  September, a PBY dispatched from Adak joined the search but to no avail. Two 
  other paragraphs from Ens. Barwick's report may or may not be significant. 
  However they are worth quoting in absences of any conclusion proof of the exact 
  fate of the men:
  "There is slight evidence that the members of the boat crew might have met with 
  enemy action been taken prisoners." And...."As yet there is no evidence such as 
  floating oars, lifejackets, pieces of wearing apparel or boat having washed 
  ashore." 
  "YP 197 advised at 1400, 28 September 1943 there their searching party had 
  found a 5-gallon oil can floating between Pinnacle Rick and this unit, which was 
  later identified as fuel can used in surf boat in which boat crew departed." Also 
  strange human footprints were found at this time on this uninhabited island.
  In addition, these paragraphs to make the mystery more complete:
  "In making trip to the Army site via water it is unnecessary to navigate more than 
  200 yards off shore at any time and men were under orders to keep within this 
  limit, as the writer made the trip several times with Haglund and Breimo 
  instructing them which course to pursue."
  "At the time the boat crew departed, the sea was calm and no difficulties were 
  encountered when launching boat through the surf."
  Unlike earlier Loran construction parties, ConDet "A" arrived at the Western end 
  of the Aleutian Islands during the latter part of 1943 with an outfit that the 
  Japanese may have had in mind when they complained of the "Unsportsmanlike 
  conduct of the war by way of vulgar display of wealth." However, the job was 
  being undertaken at the worst time of year in order to make Loran in dire need of 
  such service in the western Aleutians.
  This auspicious beginning, however was literally "the calm before" so many 
  storms that the Aleutian construction detachment began to think they had been 
  assigned to "Hell's Corner".
  Men and materials began to arrive at sites 62 (Adak) [sic], 63 (Amchitka) and 64 
  (Attu), beginning in early November 1943. Liberty ships and the Coast Guard 
  cutter CITRUS did the transporting. The Liberty ship GEORGE FLAVEL left 
  Seattle 24 October and arrived at Adak 18 November. The Liberty ship McKENZIE 
  with material and some personnel aboard arrived at Attu on 3 December after 
  stopping at Adak and Amchitka on the way.
  Since the Aleutian Islands are conceded to produce some of the world's worst 
  weather and since the coastline in that area consists mainly of mountainous 
  jagged rocks standing on end, swept by violent tides, currents and monumental 
  surf all landings were "by the grace of god" and extremely hazardous and 
  precarious. Attu undoubtedly presented the largest and most varied collection of 
  climatic and physical difficulties of the three Aleutian sites, so that a detailed 
  description of the construction there will encompass all hazards encountered in 
  the entire Aleutian operation.
  According to Lt. Comdr. Russel Yates, USCG, C.O. ConDet "A" the lack of 
  warehouse space and spare huts on Attu on arrival was acute. The Coast Guard 
  construction crew was immediately forced to erect three Quonset huts for 
  storage space at Massacre Bay, with material furnished by the Sea Bees there.
  Then the first section of the construction party left for site 62. They established a 
  temporary construction base camp at Baxter Cove, since the site survey party 
  had selected this spot as the only place anywhere near #62 where landing might 
  be possible.
  Wooden barges brought to Attu, to be used in unloading operations "were found 
  unsuitable for this location", a mild way of stating that they were smashed to 
  matchsticks on the rocks in the surf. Those left were traded for a 5x7 steel 
  pontoon type barge with removable sections, which is being extensively used by 
  all armed forces in landing operations. These pontoon barges, or "Admiral 
  Laycock's cigar-boxes", are the only type of equipment which can withstand 
  such a shoreline, since two-thirds of the section can be punctured on rocks and 
  they will still retain their buoyancy.
  Tents, mess hut and Loran transmitting equipment storage hut were erected 
  during the usual foul weather and the ubiquitous "Cat" was started on the 
  construction of the two and half mile road to the site.
  Lt. Cmdr. Yates gave the high points of this killing two and a half miles in a few 
  succinct paragraphs when he said:
  "The first five hundred feet of the road took us through an Aleutian cemetery 
  located under a dummy gun emplacement that the Japs had abandoned a few 
  months before. Desecrating an Aleut grave is a serious offense, but we were 
  unaware of it until we started turning up human skulls and bones of prehistoric 
  animals which had been in turn, buried deep below ivory trinkets and tons of bird 
  and fish bones."
  "Another midway tent was erected a mile and half from Baxter Cove to serve as a 
  mess hut and shelter during round the clock work on the road."
  "After consultation with the aerologer, it was decided to unload a large portion of 
  the building materials on 24 December. And other 5x7 steel pontoon barge was 
  borrowed from the CB's and in company of the CITRUS, both barges arrived off 
  Baxter Cove shortly after noon of that day. A heavy ground swell made unloading 
  from the cutter to the barge precarious and the unloading was further delayed by 
  increasing swells and a weather report that a sudden squall was headed our 
  way."
  In spite of conditions becoming rapidly adverse, both barges made the beach 
  about sundown and temporary floodlights were rigged. Unloading operations 
  continues all Christmas Eve and until noon on Christmas Day. By then, heavy 
  seas were tossing the barges around on the rocks men were escaping death by a 
  hair every other minute in an effort to complete the unloading and the confusion 
  that existed was like 'midshipmen on watch.'
  "The storm increased in intensity and the CITRUS was unable to maintain her 
  anchorage, (there is very little good anchoring bottom in the Aleutian area), and 
  was forced to return to Massacre Bay for shelter. All hands ashore, which 
  included some of the CITRUS' crew, remained there until the storm subsided, 2 
  January."
  Most of the materials were carried to the site from Baxter Cove on a barge sled, 
  made by the crew and pulled by the "Cat". The road was formally christened 
  Hooligan Highway and when completed was quite one of the engineering 
  wonders of Attu.
  The antenna poles were rafted and towed to Baxter Cove, then hauled over 
  Hooligan Highway by the "cat" to the site. Because of the sharp turns in the road, 
  a switchback donkey winch had to be employed. Throughout all operations 
  winds sometimes reaching velocity of 125mph raged and snow twelve feet in 
  depth paralyzed vehicular traffic for days. Only the power line survived the 
  storms and the days were filled with the struggle to push construction and at the 
  same time repair constant storm and wind ravages.
  Site 62 was out of touch with Massacre Bay for five days in early February. 
  During that time the crew erected several 90' antenna poles in ideal calm 
  weather. It was later learned that the Massacre Bay area only fifteen miles away 
  had been swept by a five day storm with 125mph winds. Mail had to be dropped 
  at the site from a plane as landings at site could only be made during the best of 
  weather, which was so seldom it would furnish food for conversation for days 
  afterwards.
  The armed services paid dearly in loss of lives for tenure of the Aleutian Island. 
  In the same storm which struck Massacre Bay, nine men were lost on an ATS tug 
  which went down only two hundred feet from the Army dock with the help unable 
  to reach them from the shore. In all the Army lost approximately fifty men during 
  January and February of 1944 in landslides and to the sea.
  At Attu, the Coast Guard was frequently called upon by the Navy COP to assist in 
  rescues and salvage work. The CITRUS took nine men off a swamped ATS tug 
  without loss of life and then sank the dying tug with gunfire. She also assisted in 
  getting the Liberty ship off the beach where it had been driven in a severe storm. 
  The members of the Coast Guard construction crew at site 62 removed nine more 
  Army men from a battered ATS power barge and received a commendation for 
  their gallantry from the Commanding General of the Area. Such rescue and 
  salvage work could have become an all-time job for the personnel for the Coast 
  Guard in the vicinity, if they could have spared the time from their regular duties 
  as in addition to the fiendish weather, the harbor at Attu was very poor with little 
  shelter and a bad "holding" bottom.
  Site 62 was located on a saddle of the hills, at an elevation of twelve hundred 
  feet. It required the use of bulldozers to reach it with materials and the 
  employment of switch backs due to the terrain and steepness of the slopes. 
  William A. Baughman, Sea. 1c was killed on the stitch back when the "cat" 
  slipped out of gear and rolled over him on its steep descent to the edge of the 
  bluff.
  The Coast Guard paid for Aleutian Chain with other lives too. Ensign Johnson, 
  C.O. of unit 64 was killed when the PBY he was in crashed making a landing in 
  Dutch Harbor. He was engaged in running baselines when it happened. Another 
  plane a Coast Guard PBY with its entire crew was lost without trace, near Point 
  Heiden, while returning to the States.
  With all these misfortunes and all nature leagued against them the Construction 
  crews in the Aleutians did a magnificent job and in an amazingly short time. 
  Three months after the landing at Baxter Cove the construction crew were 
  gradually beginning to be returned to the states. The last man left the Aleutians 
  about 15 March 1944 and the regular operational crews took over. After extensive 
  testing operations all three stations were commissioned 18 May 1944 and turned 
  over to the jurisdiction of the Aleutian Representative at Adak, Lt. Bob Kersten.
  The great significance of the construction feat in the Aleutians lies obviously in 
  the fact that in spite of the most adverse conditions the Coast Guard working 
  with the cooperation of the other armed services can erect short lengths of time. 
  A tribute indeed to splendid organization and the staunch determination of the 
  personnel engaged worthy of the tradition of the United States Coast Guard at its 
  best.
 
 
 
  Photo by Russ Marvin
 
 
 
 
 
  
  
  
 
 
  
#4. LORAN-A Station, Murder Point; established in Nov 
  1948, abandoned in Jul 1961 for newer quarters and 
  location which became the current LORAN-C Station at 
  Cosco Cove near Massacre Bay. These abandoned 
  buildings were used by the now defunct “Attours, Inc.” to 
  house tourists on birding trips to Attu Island.  (Russ 
  Marvin)
  Coordinates:  52°48'17.10"N  x  173° 9'46.28"E
 
 
  
  
  
 
 
  
#5.  Aerial View; LORAN STATION-A, Murder Point. These 
  buildings were put to use by Attours, Inc. to house their 
  Birding Tour participants after the new LORAN-C station 
  was built. Attu’s runway can be seen directly above, on 
  the other side of Casco Cove. The newer LORAN 
  STATION-C station is located on the right side of the 
  runway, near the top of the photo.  (Google Earth)
  Coordinates:  52°48'17.10"N  x  173° 9'46.28"E
 
 
  
  
  
 
 
  
#6.  2000; Attu’s LORAN-C building at Casco Cove near 
  Massacre Bay.  Established 10 Jul 1961, closed 26 Aug 
  2010. (Russ Marvin)
  Coordinates:  52°48'17.10"N  x  173° 9'46.28"E
 
 
  
  
  
 
 
  
#7. Location of newer LORAN-C buildings and antennas 
  at Casco Cove near Massacre Bay.  Closed August 2010.
  Coordinates:  52°48'17.10"N  x  173° 9'46.28"E
 
 
  
 
 
  
 
 
  
 
 
                        Updated: 12/08/2016  07:24
 
 
  
  
  
 
 
  #1.  1944-1949; LORAN-A Station, Theodore Point.  (NARA)
  The original LORAN-A station established on Attu on 
  September, 1943. Operational 1944 - 22 Jun 1949.
  Coordinates:  52°45'09"N  x  172°54'31"E
  Sourced From: Loran-History
  
 
  
  
  
 
 
  #2.  1944-1949; LORAN-A Station, Theodore Point.  
  (Google Earth)
  Coordinates:  52°45'09"N  x  172°54'31"E
  Sourced From: Loran-History
  
 
  “The first of Attu’s LORAN-A stations was initially located at Theodore Point before being 
  moved to Murder Point. Then came the new LORAN-C site which was located at Massacre Bay 
  where the current station buildings are located.
  In May 1942, the CNO requested a Coast Guard Officer having electronic engineering 
  experience be assigned to him. That was LCDR Harding.  Harding's job was the liaison with MIT 
  RADLAB which was the LORAN Project. Harding coined the term LORAN. The Coast Guard ran 
  the LORAN system since its inception. On 25 March 1959, the MEDSEA LORAN-C chain was 
  declared operational.  In true Coast Guard fashion, the CG and the LORAN system served the 
  general public as well as the USN and others in the DOD.
  The MEDSEA stations were turned over to host nations in the early 1990s. By the end of 1994 
  they stopped transmitting. The Coast Guard’s affiliation with LORAN ran from May 1942 to 
  August 2010 when transmissions were terminated…which consequently also terminated Attu’s 
  role as part of the Eastern Russian NAVAIDS Chain.
  There were LORAN signal transmissions emanating from Theodore Point beginning 11 
  February 1944 until 1 August 2010 when transmissions ceased from the current Massacre Bay 
  location. Sixty six of the sixty eight years of United States involvement with LORAN, Attu 
  stands tall as having provided the longest active period of LORAN transmissions.”
  Ardon Smith
  Theodore Point, WWII
  
 
  
  
 
 
  From Wikipedia: 
  “LORAN, short for long range navigation, was a hyperbolic radio navigation system developed 
  in the United States during World War II. It was similar to the UK's Gee system but operated at 
  lower frequencies in order to provide improved range up to 1,500 miles (2,400 km) with 
  accuracy of tens of miles. It was first used for ship convoys crossing the Atlantic Ocean, and 
  then by long-range patrol aircraft, but found its main use on the ships and aircraft operating in 
  the Pacific theatre.
  LORAN, in its original form, was an expensive system to implement, requiring a cathode ray 
  tube (CRT) display. This limited use to the military and large commercial users. Use was never 
  widespread, and by the time new receivers were available in the 1950s, the same improved 
  electronics led to new systems with higher accuracy. The US Navy began development of 
  Loran-B, which offered accuracy on the order of a few tens of feet, but ran into significant 
  technical problems. The US Air Force had worked on a different concept, known as Cyclan, 
  which the Navy took over as Loran-C. Loran-C offered longer range than LORAN and accuracy 
  of hundreds of feet. The US Coast Guard took over operations of both systems in 1958.”
  “The original LORAN was proposed by Alfred Lee Loomis at a meeting of the Microwave 
  Committee. The US Army Air Corps was interested in the concept for aircraft navigation, and 
  after some discussion they returned a requirement for a system offering accuracy of about 1 
  mile (1.6 km) at a range of 200 miles (320 km), and a maximum range as great as 500 miles 
  (800 km) for high-flying aircraft. The Microwave Committee, by this time organized into what 
  would become the Radiation Laboratory, took up development as Project 3. During the initial 
  meetings a member of the UK liaison team, Taffy Bowen, mentioned that he was aware the 
  British were also working on a similar concept, but had no information on its performance.
  The development team, led by Loomis, made rapid progress on the transmitter design and 
  tested several systems during 1940 before settling on a 3 MHz design. Extensive signal-
  strength measurements were made by mounting a conventional radio receiver in a station 
  wagon and driving around the eastern states. However, the custom receiver design and its 
  associated cathode ray tube displays proved to be a bigger problem. In spite of several efforts 
  to design around the problem, instability in the display prevented accurate timing 
  measurements.
  By this time the team had become much more familiar with the British Gee system, and were 
  aware of their work on "strobes", a time base generator that produced well-positioned "pips" 
  on the display that could be used for accurate measurement. They met with the Gee team in 
  1941, and immediately adopted this solution. They also found that Project 3 and Gee called for 
  almost identical systems, with similar performance, range and accuracy. But Gee had already 
  completed basic development and was entering into initial production, making Project 3 
  superfluous.
  In response, the Project 3 team told the Army Air Force to adopt Gee, and realigned their own 
  efforts to provide long-range navigation on the oceans. This led to US Navy interest, and a 
  series of experiments quickly demonstrated that systems using the basic Gee concept but 
  operating at a much lower frequency around 2 MHz would offer reasonable accuracy on the 
  order of a few miles over distances on the order of 1,250 miles (2,010 km), at least at night 
  when signals of this frequency range were able to skip off the ionosphere. Rapid development 
  followed, and a system covering the western Atlantic was operational in 1943. Additional 
  stations followed, covering the European side, and then a massive expansion in the Pacific. 
  By the end of the war there were 72 operational LORAN stations, and as many as 75,000 
  receivers.
  In 1958 the operation of the LORAN system was handed over to the US Coast Guard, which 
  renamed the system "Loran-A", the lower-case name being introduced at that time.”
  While researching information pertaining to LORAN station history and technical data I was 
  fortunate enough to have discovered on the United States Coast Guard’s website:
  http://www.uscg.mil/history/STATIONS/LORAN/docs/LORAN_Section_1.asp
  From this site I was able to extract an abundance of historical facts relating to the 
  development of LORAN, as well as the establishment of the LORAN station on Attu: LORSTA 
  ATTU. The following information has been extracted from that document:
  
 
  
  
  
 
 
  #3.  Google Earth image of Theodore Point’s LORAN 
  Station location.  (Joe Jester)